Case Study – Commercial Equipment Relocation and 3-Phase Rewiring

With Operational Continuity Restored

SBH Electrical completed an urgent commercial electrical upgrade involving the relocation of a homogeniser, VSD, contactor control components, and isolator closer to the switchboard to improve safety, compliance, and system functionality.

The project required 3-phase cable installation, switchboard reconnection, CAT6 termination, and testing across multiple electrical systems under time pressure on a non-compliant site. The result was a fully operational system delivered across 3 site visits, with safety risks reduced, equipment successfully recommissioned, and the client satisfied with the outcome.


  • Company: SBH Electrical
  • Client Type: Repeat client
  • Industry: Commercial / industrial electrical services
  • Service Category: Equipment relocation, 3-phase electrical installation, compliance upgrade
  • Project Type: Electrical system upgrade and reconfiguration
  • Site Type: Commercial site
  • Location: Not specified
  • Trigger for Work: Safety concern and upgrade of electrical system on a commercial site
  • Urgency: Urgent due to ongoing operational issues
  • Primary Systems Involved: Homogeniser, VSD, isolator, switchboard, CAT6 control connection
  • Electrical Scope: 3-phase cable installation, reconnection, testing, and fit-off
  • Compliance Context: Switchboard non-compliance and safety risk mitigation

The Challenge

The client needed critical plant and control components relocated and reconnected safely within an active commercial environment. The homogeniser had to be moved, and the VSD, contactor control components, and isolator needed to be relocated closer to the switchboard and then fully installed.

The job was more complex than a standard relocation because it involved non-compliant switchboard conditions, safety risks, and time pressure. The work required accurate sequencing to ensure the equipment could be made safe, rewired correctly, and brought back online without introducing further faults. Before completion, the site faced ongoing issues and operational risk. If the work had not been completed correctly, the client would have remained exposed to continued equipment downtime and unresolved electrical safety issues.

The Solution

SBH Electrical delivered the upgrade through a structured commercial installation and recommissioning process:

  • Relocated a 50A 5-pin switch and socket combo from the previous installation.
  • Ran 12 metres of insulated 10mm 3-phase cable from the 50A 5-pin switch to the VSD in conduit.
  • Terminated the 10mm cable in the VSD to complete the new connection.
  • Terminated previously installed CAT6 cable in the VSD using a CAT6 mechanism and connected it to the VSD male end.
  • Re-terminated the 10mm cable back into the switchboard after it had previously been disconnected to make the installation safe for works.
  • Tested the VSD after installation to verify that the unit was operating correctly.
  • Confirmed the downstairs control pad was working.
  • Used 5 metres of insulated 10mm 3-phase cable to install a 5-pin plug lead for the homogeniser.
  • Fitted off the plug lead using the existing cables in the homogeniser.
  • Managed the works over 3 site visits to complete the upgrade within the expected timeframe.
  • Improved the installation layout by relocating key components closer to the switchboard for safer system configuration.
blank

The Results

  • 3 site visits used to complete the works within the expected timeframe.
  • 12 metres of insulated 10mm 3-phase cable installed from the switch to the VSD.
  • 5 metres of insulated 10mm 3-phase cable used to install the homogeniser plug lead.
  • 1 x 50A 5-pin switch and socket combo relocated and reinstalled.
  • 1 VSD system reconnected, tested, and confirmed operational.
  • 1 downstairs control pad tested and confirmed operational.
  • CAT6 termination completed for the VSD control connection.
  • Switchboard reconnection completed after prior safe isolation.
  • Safety risks reduced through reconfiguration and controlled installation sequencing.
  • Operational continuity restored for the homogeniser system.
  • Client satisfaction achieved on completion of works.
blank

Summary

  • SBH Electrical completed an urgent commercial electrical reconfiguration involving a homogeniser, VSD, isolator, and switchboard-related works.
  • The project was triggered by safety concerns and ongoing electrical issues on site.
  • The site included a non-compliant switchboard condition, time pressure, and multiple system dependencies.
  • SBH Electrical installed 12 metres of 10mm 3-phase cable to the VSD and 5 metres of 10mm 3-phase cable for the homogeniser plug lead.
  • The team re-terminated the switchboard connection, completed CAT6 termination, and tested the VSD and control pad successfully.
  • The works were completed within the expected timeframe over 3 site visits.
  • The client was a repeat customer who chose SBH Electrical for reliability, communication, and quality of workmanship.

Need to Avoid Electrical Downtime in Your Operations?

Electrical downtime costs money. We deliver structured upgrades that minimize disruption and restore operations fast.


Some love from our clients

Read feedback from our satisfied customers and take a look at some of our recent electrical projects.

blank

Best experience we’ve ever had with an electrician and highly recommend Sam. Arrived on time; frequent and clear communication; Will definitely use Sam again and had no hesitation in immediately telling our neighbours and friends.

Jenny S

blank

Second time we have used Sam. He is punctual, polite and professional. A lovely guy who does a great job at a good price. We highly recommend him!

Phil. E

blank

Sam was offering free labour for electrical services for those in need in my area. I chose him to do my job because I knew he must be a good bloke. He was on time, personable, communicated my options clearly and even cleaned up after himself!

Roslyn. W

blank

Very positive experience with Sam and his business, he was very reliable with quotes for the work too, highly recommend him.

Andrea. B

blank

Sam showed up on time and did a quality job. He’s a Richmond local and I’d highly recommend. I will use SBH again.

Russell. J

blank

Absolute Legends! Was able to quote straight away, turned up on time and got things sorted straight away. Explained everything that they were doing and answered all of our questions. 100% recommend SBH and will be using them in the future!

J Robertshaw

Call Now Button